Tauranga Eastern Link reaches early milestone

Tuesday 19 April 2011, 4:11PM

By New Zealand Transport Agency

341 views

TAURANGA

It's the road you build before you build the road. The appearance of trucks and bulldozers signal that work is progressing on building the Tauranga Eastern Link's construction roads, the NZ Transport Agency (NZTA) says.

Andrew Scott, the NZTA’s Tauranga Eastern Link Principal Project Manager says construction roads will be built along the whole length of the project site to reduce the number of heavy vehicles using local roads.

“We’re committed to maximising safety and minimising disruption for local residents as we build the Tauranga Eastern Link. As well as providing easier access to the site for construction traffic, these temporary routes will also greatly reduce the amount of heavy construction traffic on local roads. This reduces congestion and safety risks associated with having an increased number of heavy vehicles on the roads.”

“The construction road for the Domain to Parton Road section of the Tauranga Eastern Link will require about 2,200 truck loads carrying approximately 40,000 cubic metres of rock material from the Poplar Lane quarry to the Domain Road end of the site,” says Mr Scott.

“Weather permitting, it will take approximately two months to build this section of construction road. During this time, large truck and trailers will be entering the site through the Domain Road roundabout onto Tara Road so we encourage motorists to take extra care when travelling through the area.”

In March, construction started on the first section of construction road from Pah Road to the eastern side of the Kaituna River. Once this is completed, ground improvement work will get underway for the 150 metre long Kaituna River bridge.

The NZTA thanks road users for their patience and cooperation during the works.

Keep up-to-date with developments at www.nzta.govt.nz/tel